Sioux Chief 865-GID Guida d'installazione

Tipo
Guida d'installazione
Always wear protective gear and observe safety precautions when installing the FastTrack system.
Plan/Excavate
Excavate a trench for the FastTrack, considering both load
class and slab thickness. All channels must be encased
on three sides with a minimum of 4" of concrete. For
slabs thicker than 4", encasement must be equal to slab
thickness. The engineer should determine slab thickness
Concrete encasement is required regardless of surface
type (concrete, asphalt, pavers, etc.).
Expansion joints will be needed on each side of the trench,
an expansion joint.
to use as a guide.
Layout Channels
Lay out the channels, in order, alongside the excavated
trench, starting with the deepest point and working back.
saw. Attach the end outlet with screws to the deep end
and the end cap on the shallow end. If using an end outlet,
outlet and pipe.
For Bottom Outlet: Using a hole saw, open the bottom
outlet in the deep end and install end caps on
both the deep and shallow ends.
Assemble Channels
Set channel sections in order into the trench. Beginning
at the outlet end, connect the channels together using
silicone sealant in the groove if desired.
If Using Iron Grate Frames: Remove the construction
covers and install iron grate frames. Reinstall the
construction covers in the frames.
Slide the construction covers (downstream) such that
they overlap the joint - this will help prevent misalignment
at the joints.
MIN
Trench Drain Installation Guide
Cover Joint
Channel Joint
Anchor with Rebar
Beginning at the outlet end, install rebar into the anchor
clips on either side of the channel and drive rebar into the
ground. Adjust channel vertically to the proper elevation,
checking for level and alignment using the string line as a
guide. The top of the channel should be set 1/16" to 1/8"
When the channel is in proper position, secure the rebar into
the anchor clips using screws or tie-wire to lock in place.
Continue the installation with upstream sections, setting
with rebar, checking for elevation, level, and alignment
until all channel sections are set.
Set with Concrete
with rebar and screws (wire) in ALL available anchor clips
to keep the run as secure as possible. Be Sure:
Channels will be encased in 4" of concrete (min.)
Expansion joints will be installed on each side
Connect drain piping to the channel outlet according to
plans using a No-Hub coupling.
Set concrete “pads” around rebar, under and on sides
of the channels to prevent movement or misalignment
Pour the concrete slab around the installation and
vibrate to eliminate voids in the pour.
Final Inspection
the construction covers. Inspect the installation to be
sure channels and drain piping are free of debris. Set
appropriate grating in place and secure the grates into
the grate anchors using screws.
www.siouxchief.com
Supply Drainage Support
  • Page 1 1
  • Page 2 2

Sioux Chief 865-GID Guida d'installazione

Tipo
Guida d'installazione

in altre lingue